Subway stations are smooth; Seepz, MIDC, Marol Naka on Metro 3 completed

1 minute, 14 seconds Read
Spread the love

[ad_1]

m. Ta. Special Representative, Mumbai : The deadline for the Seepz-Bandre-Kulaba Metro 3 route is set for December. With seven months left for it, the important stations of Seepz, MIDC and Marol Naka on this route have been completed. These stations are set up underground in heritage buildings, offices and congested areas. These stations are considered to be a feat of engineering skill, without disturbing the buildings, factories, offices and residents on the ground.Metro 3 is the first underground metro project in the state. Underground metro projects have also been completed in other places in the country. In it, it is mentioned that the work of Delhi Metro is challenging. The work of Metro 3, which connects Mumbai’s western suburbs from north to south, has been challenging. This work is being completed rapidly by the Mumbai Metro Rail Corporation Limited (MMRC), which is building this line.

– Seepz
The offices of various companies are located in the premises of this station.
97.20 percent of station construction and 85.70 percent of system related works have been completed.

-MIDC
This station is located under various small and big factories.
98 percent of station construction and 86.40 percent of system related works have been completed.

Summer vacation turns out to be a game changer, metro connecting Dahisar is preferred by tourists, new update on ridership
– Marol nose
Constant rush and traffic jams have to be faced in this station area.
94.30 percent of station construction and 70.80 percent of system related works have been completed.